Iberdrola switches on 210 GWh Spanish pumped hydro-battery project

Source:pv magazine

Iberdrola Spain has started commissioning the 225 MW Valdecañas pumped hydro energy storage (PHES) plant, which is hybridized with a 15 MW/7.5 MWh battery energy storage system.

 

Image: Iberdrola

Share

From ESS News

Spanish utility Iberdrola has begun commissioning the first stage of the Valdecañas pumping station near Cáceres, in the autonomous community of Extremadura.

The completed hydroelectric site will have a 225 MW generation capacity plus a 15 MW/7.5 MWh hybrid battery and will add 210 GWh of energy storage capacity to the local Tajo grid.

Iberdrola said the project has used existing infrastructure at the site, including electricity transmission lines, and did not need to alter the levels of the Valdecañas and Torrejón-Tajo reservoirs. The fact the work has been purely electromechanical ensures it has had minimal environmental impact.

Declaration: The content quoted and reproduced from other organizations and websites is intended to convey more information rather than for profit. It does not represent endorsement of their views or verification of their descriptions; the content is for reference only. Copyright belongs to the original authors. If there is any infringement, please contact us for removal.